Five stages control at construction

Five stages control at construction

As the demand for complex cleanrooms in the life sciences grows, construction challenges mount. Making the right decisions during the building and commissioning phases of cleanrooms will help to ensure that they are successful, better integrated, more operable and sustainable. Generally speaking, teamwork among designers, operators, maintenance people and builders that focuses on project timelines will achieve the best results. The suggestions below will help drug and device manufacturers step back and better envision the whole facility during the build process.

Stage

Operation

Duration

Cleaning procedure

Requirement

Level 1

Early Stage of Construction  Site

Before Ceiling Grid and Flooring

a. Clear Garbage Everyday;
b. Keep Work Place Clean;
c. Check Material Storage Everyday and Keep Garbage at Waste Storage Site;

a. No Smoking, Drinking and Playing;
b. Wielding and Duct Cutting Have to Operate at Place Equipped with Fire Extinguisher;
c. Drilling and Cutting  Operation Need to Apply Vacuum Technology;

Level 2

Ceiling grid. Flooring and Setup Perimeter

Before AHU Testing

A .Clear Garbage Everyday;
b. Check Material Storage Everyday and Keep Garbage at Waste Storage Site;

a. Set Security Checkpoint, 2-3 Entrance;
b. Unwrap All Material and Wrap with Paper or Wood Packing Material;
c. Vacuum Cleaning in Daily Basis and Keep Ceiling, Wall and Tools Clean;

Level 3

AHU Testing

Before Installation of HEPA

a. Vacuum and Floor Cleaning on Material Sent to Workplace;
b. Vacuum Cleaning at Entrance Point Everyday;
c. Sticky Pad at Entrance of Clean Room;

a. Only 1 Entrance;
b. No Wood or Paper Material Allow;
c. Floor Protection at Construction Site;
d. Get Permission for Following Action: Drilling, Polishing, Wielding,  Spraying, Drilling, Cutting etc;

Level 4

Installation of HEPA

Before Checking/ Testing

a. At Least 3 Times of Vacuum Cleaning and Floor Washing;
b. Tools Need to Clean of Dust and Oil , Wire Need to in Good Condition Before Enter Clean Room;

a. 1 Entrance / Exit Point;
b. Need Registration for Every Entry;
c. All Tools Need to Meet Specification;
d. No Wood and Paper Product in Clean Room;
e. Floor Protection on Work Floor;

Level 5

System Testing /Checking in Cleanroom

Before Hand on to Owner

A. Rub Cleaning in Daily Basis;
b. At Least 3 Time of Vacuum Cleaning and Floor Washing;
c. Vacuum the Floor with No Cover;

a. 1 Entrance / Exit Point;
c. Need Registration for Every Entry;
d. All Tools Need to Meet Specification;
e. No Wood and Paper Product in Clean Room;
f. Get Permission for Following Action: Drilling, Polishing, Wielding, Spraying, Drilling, Cutting etc;

 Resources & Articles

CLIN ® "Resources" page is for individuals/companies seeking information on cleanrooms and controlled environments. Find Cleanroom News, Discussion Forums, Cleanroom Cleaning Recommendations, Cleanroom Terminology, Cleanroom Directory, and more.

 Content Disclaimer

Information are contributed by/from different websites and all credit goes to its respective owners/writers/websites/companies and etc, and while we endeavour to keep the information up to date and correct, we make no representations or warranties of any kind, express or implied, about the completeness, accuracy, reliability, suitability or availability with respect to the website or the information, products, services, or related graphics contained on the website for any purpose. Any reliance you place on such information is therefore strictly at your own risk.

In no event will we be liable for any loss or damage including without limitation, indirect or consequential loss or damage, or any loss or damage whatsoever arising from loss of data or profits arising out of, or in connection with, the use of this website.

Through this website you are able to link to other websites which are not under the control of respective owners/writers/websites/companies and etc. We have no control over the nature, content and availability of those sites. The inclusion of any links does not necessarily imply a recommendation or endorse the views expressed within them.

Every effort is made to keep the website up and running smoothly. However, CLIN ® takes no responsibility for, and will not be liable for, the website being temporarily unavailable due to technical issues beyond our control.

We are experienced in Cleanroom Solutions

Call Us for Consultation +6(04) 398 1778

About CLIN

Cleanroom Industries Sdn. Bhd. was founded in 1999 as a pioneer manufacturer in Malaysia specializing in design and manufacture of a full range of cleanroom-related architectural products for cleanroom applications up to Class 1 cleanliness.

Awards & Recognitions

ISO 9001 Malaysia Power Brand Super Excellent Brand Sirim QAS Made in Malaysia Asia Pacific International Honesty Enterprise Keris Award